Strategy, Finance & City
Regeneration
Agenda Item 25
Committee
Subject:
|
Targeted Budget
Management (TBM) 2023/24:
Month 2 (May)
|
Date of Meeting:
|
13 July 2023
|
Report of:
|
Chief Finance
Officer
|
Contact Officer:
|
Name:
|
Jeff Coates
|
Tel:
|
29-2364
|
|
Email:
|
Jeff.Coates@brighton-hove.gov.uk
|
Ward(s)
affected:
|
All
|
FOR GENERAL RELEASE
1
PURPOSE OF REPORT AND POLICY CONTEXT:
1.1
The Targeted Budget Monitoring (TBM) report is a key component of
the council’s overall performance monitoring and control
framework. This report sets out an early indication of forecast
risks as at Month 2 on the council’s revenue and capital
budgets for the financial year 2023/24.
1.2
The forecast risk for 2023/24 at this early stage is a
£11.101m overspend on the General Fund revenue budget. This
includes a forecast overspend of £4.823m on the
council’s share of the NHS managed Section 75 services.
Forecasts at this stage of the year are based on early trends and
are more difficult to predict with high accuracy, particularly in
relation to those areas subject to seasonal variation. There are
also some ongoing impacts in relation to economic conditions which
are currently suppressing incomes such as planning fees and
commercial rents as well as continuing to drive higher Council Tax
Reduction claimant numbers. A significant level of savings are also
shown to be at risk with the report indicating that £2.947m
(23%) of the substantial savings package in 2023/24 of
£13.043m is potentially at risk.
2
RECOMMENDATIONS:
2.1
That the Committee note the forecast risk position for the General
Fund, which indicates a potential forecast overspend risk of
£11.101m. This includes an overspend of £4.823m on the
council’s share of the NHS managed Section 75 services.
2.2
That the Committee note the escalated recruitment and spending
controls summarised in Section 12 that have been applied from 3
July to assist in mitigating the overspend forecast over the
remaining months of the financial year.
2.3
That the Committee note the forecast for the Housing Revenue
Account (HRA), which is currently an overspend of
£0.160m.
2.4
That the Committee note the forecast position for the Dedicated
Schools Grant which is currently an overspend of
£1.155m.
2.5
That the Committee note the forecast outturn position on the
capital programme which is a forecast underspend of £2.470m
and approve the variations and slippage in Appendix 5 and new
schemes as set out in Appendix 6.
3
CONTEXT/ BACKGROUND INFORMATION
Targeted Budget
Management (TBM) Reporting Framework
3.1
The TBM framework focuses on identifying and managing financial
risks on a regular basis throughout the year. This is applied at
all levels of the organisation from Budget Managers through to
Strategy, Finance and City Regeneration Committee. Services monitor
their TBM position on a monthly or quarterly basis depending on the
size, complexity or risks apparent within a budget area. TBM
therefore operates on a risk-based approach, paying particular
attention to mitigation of growing cost pressures, demands or
overspending through effective financial recovery planning together
with more regular monitoring of high risk demand-led areas as
detailed below.
3.2
The TBM report is normally split into the following sections:
i)
General Fund Revenue Budget Performance
ii)
Housing Revenue Account (HRA) Performance
iii)
Dedicated Schools Grant (DSG) Performance
iv) NHS
Controlled S75 Partnership Performance
v)
Capital Investment Programme Performance
vi)
Capital Programme Changes
vii)
Implications for the Medium Term Financial Strategy (MTFS)
viii) Comments of the Chief
Finance Officer (statutory S151 officer)
4
General Fund Revenue Budget Performance (Appendix 3)
4.1
The table below shows the provisional outturn for Council
controlled revenue budgets within the General Fund. These are
budgets under the direct control and management of the Executive
Leadership Team. More detailed explanation of the variances can be
found in Appendix 3.
2022/23
|
|
2023/24
|
Forecast
|
Forecast
|
Forecast
|
Provisional
|
|
Budget
|
Outturn
|
Variance
|
Variance
|
Outturn
|
|
Month 2
|
Month 2
|
Month 2
|
Month 2
|
£'000
|
Directorate
|
£'000
|
£'000
|
£'000
|
%
|
2,837
|
Families, Children & Learning
|
63,514
|
64,545
|
1,031
|
1.6%
|
(2,138)
|
Health & Adult Social Care
|
106,516
|
109,213
|
2,697
|
2.5%
|
98
|
Economy, Environment & Culture
|
41,001
|
43,214
|
2,213
|
5.4%
|
(92)
|
Housing, Neighbourhoods & Communities
|
22,844
|
24,907
|
2,063
|
9.0%
|
(308)
|
Governance, People & Resources
|
31,803
|
31,803
|
0
|
0.0%
|
397
|
Sub Total
|
265,678
|
273,682
|
8,004
|
3.0%
|
2,623
|
Corporately-held Budgets
|
(19,811)
|
(16,714)
|
3,097
|
15.6%
|
3,020
|
Total General Fund
|
245,867
|
256,968
|
11,101
|
4.5%
|
4.2
The General Fund includes general council services, corporate
budgets and central support services. Corporate Budgets include
centrally held provisions and budgets (e.g. insurance) as well as
some cross-cutting value for money savings targets. Note that
General Fund services are accounted for separately to the Housing
Revenue Account (Council Housing). Note also that although part of
the General Fund, financial information for the Dedicated Schools
Grant is shown separately as this is ring-fenced to education
provision (i.e. Schools). The chart below shows the monthly
forecast variances for 2023/24 and the previous three years for
comparative purposes.
Demand-led Budgets
4.3
There are a number of budgets that carry potentially higher
financial risks and therefore could have a material impact on the
council’s overall financial position. These are budgets of
corporate significance where demand or activity is difficult to
predict and where relatively small changes in demand can have
significant implications for the council’s budget strategy.
These can include income related budgets. These therefore undergo
more frequent and detailed analysis.
2022/23
|
|
2023/24
|
Forecast
|
Forecast
|
Forecast
|
Provisional
|
|
Budget
|
Outturn
|
Variance
|
Variance
|
Outturn
|
|
Month 2
|
Month 2
|
Month 2
|
Month 2
|
£'000
|
Demand-led
Budget
|
£'000
|
£'000
|
£'000
|
%
|
943
|
Child Agency & In House Placements
|
26,906
|
27,027
|
121
|
0.4%
|
933
|
Community Care
|
71,746
|
79,915
|
8,169
|
11.4%
|
734
|
Temporary Accommodation
|
9,898
|
12,399
|
2,501
|
25.3%
|
2,610
|
Total Demand-led Budget
|
108,550
|
119,341
|
10,791
|
9.9%
|
The chart below
shows the monthly forecast variances on the demand-led budgets for
2023/24.
TBM Focus Areas
There are clearly
widespread pressures across most areas of the council, particularly
front-line, demand-led areas which is a clear indicator of the
inflationary and demand pressures driven by current economic
conditions. Key areas of pressures are outlined below:
4.4
Families, Children & Learning: The current projected
position identifies potentially significant cost pressures:
£0.562m on Home to School transport, £0.373m on
Schools’ PFI, £0.140m on Children’s Disability
Payments, and £0.133m Commissioning and Brokerage. These,
together with other variances of (£0.177m) result in a
forecast overspend of £1.031m overspend as at Month 2.
·
Home to School
Transport There are several
factors contributing to overspends in Home to School Transport.
These include increased demand on the service (both at 5-16 ages,
and 16 up until 19th birthday), increased numbers of children
requiring single occupancy journeys, lack of local SEND school
sufficiency, and increased numbers of routes required to
accommodate individual post 16 learners’ timetables. Market
forces within SEND transport are also contributing to overspend in
Home to School Transport. The service is being increasingly
impacted by local driver, vehicle passenger assistant, vehicle
shortages and increased running costs. There is also a lack of
competition in the transport market, particularly minibus
providers, which is pushing up contract prices still further. There
is increasingly less capacity in the local system to meet
increasing demand, not just in the numbers of children requiring
transport but the nature of the transport requirements.
·
Children in Care
and Care Leavers: The post
pandemic period has seen children with increasingly complex needs
coming into care, as well as problems in foster care recruitment
causing an acute sufficiency issue making placing children in
families either in-house or with external providers very difficult.
This has inevitably led to increasing numbers of children being
placed in residential homes or very expensive semi-independent
placements. The impact of the increasing complexity of need has
resulted in a small number of very high-cost placements with a
combined cost of £1.821m at an average unit cost of
£11,607 per week. The number of care leavers requiring
financial support for accommodation has been steadily rising for
some time.
As at 31st May
2023 there were 151 care leavers in receipt of financial support
compared with 134 at the start of the 2022/23 financial year
– a rise of 13%. The result is the forecast overspend for
care leaver expenditure. There are currently a number of ongoing
initiatives and alternative service offers, attempting to reverse
the trend of reducing foster carer numbers and address the complex
needs of the children being referred. Including a revised and
enhanced foster carer allowance structure, new foster care
recruitment and supervision practices, Early Help and alternative
family support provision. Dependent on the relative success of
these initiatives, it is anticipated that placements for children
in care and care leavers will remain within budget in
2023/24.
·
Schools
PFI: The
Schools’ PFI (Private Finance Initiative) was set up in 2003
to improve the facilities at four schools within the city - Dorothy
Stringer, COMART (now closed), Patcham High and Varndean –
using private finance to fund the capital improvements. The scheme
runs for 25 years and a Special Purpose Vehicle (a legal entity
created to fulfil specific or temporary objectives) “Brighton
& Hove City Schools Ltd” was set up as part of it. This
is currently owned by SEMPERIAN. The scheme is funded partly by a
DfE grant with schools paying an annual charge back to the council
and partly via an annual drawdown of earmarked reserves. The annual
charge is updated each March for the RPIX (RPI All Items Excluding
Mortgage Interest) for the 12 months to February. Once the 25-year
period is complete (~ 31st March 2028) the contract with SEMPERIAN
ends and the assets will be transferred back to the
council.
The forecast for the 2023/24 central
Dedicated Schools Grant is currently an overspend of £1.155m.
More details are provided in Appendix 3.
4.5
Adults Services: The service faces significant challenges in
2023/24 in mitigating the risks arising from increasing demands
from client needs, supporting more people to be discharged from
hospital when they are ready and maintaining a resilient local
provider market. It is to be noted that this is after applying
service pressure funding of £9.639m in 2023/24 which has been
used to fund budget pressures resulting from the increased
complexity and costs of care.
The 2023/24 savings
plan for HASC totals £4.316m. There are continued actions
focussing on attempting to manage demand on and costs of community
care placements across Assessment Services and making the most
efficient use of available funds.
The forecast does
not include any additional funding from Health except those areas
already identified in the Financial Recovery Plan. The additional
temporary funding from Health in the last 2 financial years has
averaged £0.753m per annum.
The HASC
directorate has a Modernisation Programme which aims to implement a
consistent strengths-based approach across key work streams,
ensuring robust pathways are in place, developing a community
reablement offer and re-designing the front door service. Currently
the Health & Social Care system is under considerable pressure,
and this is generating additional costs for the council due to:
·
Pressures on the
system due to short-term grant monies and no long-term funding
solution;
·
Significant
pressures on the acute hospital resulting in increased costs to
support timely discharge into residential and nursing home
care;
·
Pressures on NHS
outreach and other preventative services including community
nursing (known as Integrated Primary Care Teams);
·
Workforce
capacity challenges across adult social care services;
The funding of all care packages is
scrutinised for Value for Money, ensuring that eligible needs are
met in the most cost-effective manner which will not always meet
people’s aspirations. Established safeguards are in place to
provide assurance within this process.
4.6
Temporary
Accommodation: The current forecast overspend in this
service is driven by an increase in demand for temporary
accommodation since January 2023 together with an increase in the
rental costs of the accommodation. As a result of these pressures,
the service is forecasting to overspend by £2.501m and
£1.023m of the savings target for Homelessness will not be
met. The overspend relates to the following elements:
Emergency nightly booked (spot
Purchased) accommodation is forecast to overspend by £1.295m.
The trend of increasing emergency accommodation numbers is
continuing into 2023/24. Since April the council has housed an
average of 153 households every night which is almost three times
higher than budgets allow. This is driven largely by an increase in
private property owners selling properties and evicting tenants as
a result. There is also an increase in the number of households
being placed who are fleeing from domestic abuse. The service is
analysing each placement to identify any opportunities to better
prevent homelessness and understand the reasons for this and
whether this is a sign of a wider trend in increasing demand due to
the hardship people are facing as a result of the higher cost of
living. The average nightly rate has also increased as there are
fewer, more affordable properties available.
The service is also facing further
pressures on the overall costs of block booked emergency
accommodation. The budget assumed that there would be a reduction
of 125 units during 2023/24. However, this is now looking
increasingly unlikely due to the demands on the service and the
forecast assumes no reduction in the number of households supported
during 2023/24. This impacts on the ability of the service to meet
its savings targets, as mentioned above. Additionally, the council
is facing large increases to contract costs and therefore the
forecast is that this budget will overspend by £2.114m.
Leased TA is forecast to overspend by
£0.151m, most of which relates to the extra cost from the
loss of Housing Benefit Subsidy. There is also a forecast overspend
on staffing costs associated with the Temporary Accommodation
service of £0.041m.
These variances have been offset by
further grant funding from DLUHC of (£1.100m) more than
budgeted in 2023/24.
Housing is continuing to seek cost
reductions through the continuation of the Homelessness
Transformation Programme which is an ‘end to end’
improvement programme to help the service improve its processes to
reduce the use and length of stay in Temporary Accommodation by
improving homeless prevention and enabling move on to more
sustainable accommodation. This is challenging in a city where
private sector rents are very high, supply is limited, and benefit
levels remain static. Further efficiencies will be sought as part
of an urgent financial recovery plan which aims to reduce costs by
£0.600m by reducing the use of expensive nightly booked
accommodation and also the average nightly charge by seeking more
cost-effective opportunities. Also, by (for example) continuing to
improve the prevention of homelessness, endeavouring to get the
best prices for all temporary and emergency accommodation;
improving void turnaround times in emergency accommodation, and
improving income collection thereby continuing to reduce costs in
line with the budget strategy.
4.7
Environment, Economy & Culture: The Directorate
has substantial income budgets for parking, planning and venues and
for the council’s commercial property portfolio, all of which
are dependent on visitor numbers and commercial activity. There are
also challenging savings in year of which most relate to additional
income. Of the £4.727m savings proposed for the current
financial year £3.338m net of pressures is achieved or
anticipated to be achieved, with the remaining £1.389m at
risk. Price increases have been applied in most areas, with other
increases due to be implemented in the coming months, however the
anticipated income has yet to be achieved as these areas are
dependent on demand including tourism and visitor numbers. The most
significant areas of shortfall are £0.941m for parking tariff
and permit fees increases, £0.100m on the lifeguard service
due to the delayed implementation of the budget saving to ensure a
full summer season this year, and £0.165m pressure on new and
increased commercial income targets.
4.8
These activities and services had been heavily impacted by COVID-19
in previous years and the services are starting to see recovery,
but these targets will only be achieved if demand returns fully to
pre covid levels including paid parking, tourism and venues
incomes, commercial activities and Planning & Building Control
fee incomes. The directorate also contains large budgets for the
waste collection and street cleansing services which are
forecasting greater than budgeted costs due to agency cover of
vacant posts and greater uptake on the pension scheme over recent
years adding staffing pressures to existing budgets.The overall
effect of these factors is a forecast risk of £3.233m for
Month 2. The Directorate is applying financial recovery measures of
reviewing expenditure budgets and income potential throughout the
year to address budget overspends. These financial recovery
measures will seek to reduce the forecast risk to
£2.213m.
4.9
Corporately-held Budgets There is a forecast overspend of
£3.097m on corporately-held budgets, however, this is
primarily because the projected additional costs of the NJC Local
Government 2023/24 pay award are held on this budget line. The
projected additional cost is £3.700m which is based on the
employers’ pay award offer of a £1,925 flat rate
increase or 3.88%, whichever is greater, for all NJC salaries plus
the agreed pay award of 3.50% for JNC Chief Officers. This is
equivalent to a 6.0% increase on the payroll compared with the
3.75% increase included in the budget for 2023/24.
There is also an
estimated pressure of £0.400m on Housing Benefit subsidy.
There is insufficient data to make a detailed forecast but based on
last year's outturn an overspend of at least £0.400m is
expected. The forecast will be updated as soon as more data is
available.
These pressures are
partially offset by a forecast underspend of £0.930m on the
Financing Costs budget. This is due to improved investment income
following Increases in the Bank of England Base Rate and cash
balances.
Monitoring Savings
4.10
The savings package approved by full Council to support the revenue
budget position in 2022/23 was £13.043m following directly on
from a £10.509m savings package in 2022/23. This is very
significant and follows 13 years of substantial packages totalling
over £209m, since government grant reductions commenced in
2009/10, that have been necessary to enable cost and demand
increases to be funded alongside managing the reductions in central
government grant funding.
4.11
Appendix 3 provides a summary of savings in each directorate and
indicates in total what is anticipated/achieved, what has been
offset by in year pressures and the net position of savings at
risk. Appendix 4 summarises the position across all directorates
and presents the entire savings programme. The graph below provides
a summary of the position as at Month 2 and shows that gross
savings of £11.205m have been achieved but that inflationary
pressures (exceptional price increases) have reduced this by
£1.109m leaving a total of £2.947m (23%) currently at
risk. This includes £1.838m of unachievable or unachieved
savings.
5
Housing Revenue Account Performance (Appendix 3)
5.2
The forecast outturn is an overspend of £0.160m and more
details are provided in Appendix 4. The investment made for the
2023/24 HRA budget went some way to address these issues, but
inevitably pressures have surfaced since the budget was formally
agreed at Full Council in February 2023, some of which are
described below.
5.3
The 2023/24 budgets include an allowance for a pay award of 4%
across all posts, this added £0.804m to the salary budgets
for the financial year. It is anticipated that the pay offer will
exceed this with the latest estimates resulting in a further
£0.418m being added to the 2023/24 base salary budgets. The
total increase is equivalent to a 5.6% increase on payroll compared
to the 4% already allowed for, this will be funded from Direct
Revenue Funding during 2023/24 and will form part of the base
budget for 2024/25.
5.4
The empty properties recovery working group continues during
2023/24 to address the rent loss and other costs such as the cost
temporary accommodation, council tax and repairs associated with
those empty properties. There is an expected overspend on void rent
loss during 2023/24, this is in part due to a greater number of new
affordable homes being delivered during the year than was
anticipated at the time of setting the budget. This overspend has
been offset by the increase in income from those new homes.
5.6
A committee report was presented to Housing Committee on
23rd June 2023 outlining the high level implications of
Health & Safety update on the HRA. The report updated Housing
Committee on the key outcomes, actions to date, and resourcing
plans arising from our Housing health & safety review against
the following six areas of compliance and assurance: fire safety;
asbestos; electrical safety; gas / fuel safety; lifts and lifting
equipment; water safety. The timing of investment means the
financial implications for 2023/24 are such that the costs can be
managed within the existing resources already approved.
Implications for 2024/25 and beyond will be included in the 2024/25
HRA budget report.
5.8
The service will continue to review spend to try to reduce this
forecast overspend during the year. If this cannot be managed
within budget then the overspend will be met from other HRA
resources including reviewing the revenue contribution to capital
and reserves position, as outlined in the HRA budget report for
2023/24 the level of reserves continues to be monitored.
6
Dedicated Schools Grant Performance (Appendix 3)
6.1
The Dedicated Schools Grant (DSG) is a ring-fenced grant within the
General Fund which can only be used to fund expenditure on the
schools budget. The schools budget includes elements for a range of
services provided on an authority-wide basis including Early Years
education provided by the Private, Voluntary and Independent (PVI)
sector, and the Individual Schools Budget (ISB) which is divided
into a budget share for each maintained school. The forecast
outturn is currently an overspend of £1.155m and more details
are provided in Appendix 3. Under the Schools Finance Regulations
any underspend or overspend must be carried forward within the
schools budget in future years.
7
NHS Managed S75 Partnership Performance (Appendix 3)
7.1
The NHS Trust-managed Section 75 Services represent those services
for which local NHS Trusts act as the Host Provider under Section
75 Agreements. Services are managed by Sussex Partnership
Foundation Trust (SPFT) and include health and social care services
for Adult Mental Health and Memory and Cognitive Support
Services.
7.2
This partnership is subject to separate annual risk-sharing
arrangements and the monitoring of financial performance is the
responsibility of the respective host NHS Trust provider.
Risk-sharing arrangements result in financial implications for the
council where a partnership is underspent or overspent at year-end
and hence the performance of the partnership is included within the
forecast outturn for the Health & Adult Social Care
directorate. An overspend of £4.823m is currently forecast
and more details are provided in Appendix 3.
8
Capital Programme Performance and Changes
Directorate
|
Reported Budget Month 2
|
Forecast Outturn Month 2
|
Forecast Variance Month 2
|
Forecast Variance Month 2
|
|
£'000
|
£'000
|
£'000
|
%
|
Families, Children
& Learning
|
19,544
|
19,509
|
(35)
|
-0.2%
|
Health & Adult
Social Care
|
2,300
|
2,384
|
84
|
3.7%
|
Economy, Environment
& Culture
|
90,239
|
90,239
|
0
|
0.0%
|
Housing,
Neighbourhoods & Communities
|
4,883
|
4,883
|
0
|
0.0%
|
Housing Revenue
Account
|
96,594
|
94,075
|
(2,519)
|
-2.6%
|
Governance, People
& Resources
|
5,736
|
5,736
|
0
|
0.0%
|
Total
Capital
|
219,296
|
216,826
|
(2,470)
|
-1.1%
|
(Note: Summary may include minor
rounding differences to Appendix 5)
8.2
Appendix 5 shows the changes to the capital budget and Appendix 6
provides details of new schemes for 2023/24 to be added to the
capital programme which are included in the budget figures above.
Strategy, Finance and City Regeneration Committee’s approval
for these changes is required under the council’s Financial
Regulations. The following table shows the movement in the capital
budget since approval at Budget Council.
Summary of Capital Budget
Movement
|
Reported Budget Month 2
|
|
£'000
|
Original
Budget
|
207,369
|
Changes reported at
other committees and already approved
|
6,755
|
New schemes to be
approved in this report (see Appendix 6)
|
2,654
|
Variations to budget
(to be approved)
|
5,525
|
Reprofiling of
budget (to be approved)
|
(3,007)
|
Slippage (to be
approved)
|
0
|
Total
Capital
|
219,296
|
8.3
Appendix 5 also details any slippage into next year. However, as
normal, project managers have forecast that none of the capital
budget will slip into the next financial year at this early
stage.
9
Implications for the Medium Term Financial Strategy (MTFS)
9.1
The council’s MTFS sets out resource assumptions and
projections over a longer term. It is periodically updated
including a major annual update which is included in the annual
revenue budget report to Strategy, Finance and City Regeneration
Committee and Full Council. This section highlights any potential
implications for the current MTFS arising from in-year TBM
monitoring above and details any changes to financial risks
together with any impact on associated risk provisions, reserves
and contingencies. Details of Capital Receipts and Collection Fund
performance are also given below because of their potential impact
on future resources.
9.2
The forecast risk at month 2 indicates that a significant number of
service areas are under pressure. Spending and recruitment
controls, alongside continuing development of other financial
recovery actions, will attempt to mitigate the in-year position but
should also be undertaken so as to address underlying pressures
wherever possible to alleviate ongoing pressures and improve longer
term financial sustainability.
Capital Receipts Performance
9.3
Capital receipts are used to support the capital programme. Any
changes to the level of receipts during the year will impact on
future years’ capital programmes and may impact on the level
of future investment for corporate funds and projects such as the
Strategic Investment Fund, Modernisation Fund, Asset Management
Fund and the Information, Technology and Digital Investment Fund.
The planned profile of capital receipts for 2023/24, as at Month 2,
is £8.840m which includes receipts expected for Patcham Court
Farm, Kings Road, Montague Place, HRA land transfers and some large
lease re-gear payments on commercial sites. To date there have been
receipts of £0.047m in relation to some minor lease payments,
lease extensions and loan repayments. The capital receipts
performance will be monitored over the remainder of the year
against capital commitments
Collection Fund Performance
9.5
The collection fund is a separate account for transactions in
relation to council tax and business rates. Any deficit or surplus
forecast on the collection fund relating to council tax is
distributed between the council, Sussex Police and Crime
Commissioner and East Sussex Fire Authority, whereas any forecast
deficit or surplus relating to business rates is shared between the
council, East Sussex Fire Authority and the government.
9.6
The council tax collection fund is forecast to be in deficit by
£1.233m for the financial year. The council tax reduction
(CTR) claimant numbers are higher than assumed in the tax base
calculation and basing the forecast on this continuing increase
through to year end results in an increased cost of £1.254m.
There are other areas such as probate exemptions and single person
discounts (SPD) that are currently above forecast levels. The
forecast to year end assumes for probate exemptions that the
clearance of backlog items will bring this down to budgeted level.
There is an SPD review exercise currently taking place and it is
anticipated that this will bring the forecast spend down over the
coming months. The council's share of the overall deficit of
£1.233m is £1.042m.
9.7
The business rates collection fund is forecasting a break-even
position for the financial year. There are a range of risks that
could change this forecast significantly with the main uncertain
factors being business failures and any step increase in empty
properties.
Reserves, Budget
Transfers and Commitments
9.8
The creation of reserves, the approval of budget transfers
(virements) of over £0.250m, and agreement to new financial
commitments of corporate financial significance that are not
provided for in the approved budget and policy framework require
Strategy, Finance and City Regeneration Committee approval in
accordance with the council’s Financial Regulations and
Standard Financial Procedures. There are no items requiring
approval at this stage.
10
ANALYSIS & CONSIDERATION OF ANY ALTERNATIVE OPTIONS
10.1
The provisional outturn position on the General Fund is an
overspend of £11.101m. This includes a forecast overspend of
£4.823m on the council’s share of the NHS managed
Section 75 services. Any overspend at year-end would either need to
be carried forward or potentially met from available one-off
resources.
11
COMMUNITY ENGAGEMENT & CONSULTATION
11.1
No specific consultation has been undertaken in relation to this
report.
12.1
The forecast outturn risk of £11.101 million at Month 2
represents 4.5% of the net General Fund budget. This early forecast
indicates a number of significant demand and cost pressures
alongside income pressures, some of which are driven by ongoing
economic conditions and persistently high inflation. Directorates
and services will work on actions to mitigate the position,
particularly in relation to savings plans at risk, and will develop
recovery actions wherever possible.
12.2
The position is not dissimilar to 2022/23 where very high inflation
led to significant pressures. The detailed forecasts in this report
indicate that both demand and inflation are not subsiding in many
areas and in some areas continue to grow at unprecedented rates,
for example, Home-to-School Transport. The forecast overspend is of
sufficient magnitude to be potentially destabilising to the
authority’s financial sustainability if it is not managed
down and would impact on the Working Balance and reserves. Services
will continue to develop Financial Recovery Plans as required by
the TBM framework, but escalated, corporate recruitment and
spending controls are also required in this situation and have
therefore been applied with effect from 3 July until further
notice. The controls will be managed by Directorate Management
Teams (DMTs) with oversight from the Executive Leadership Team
(ELT) and members (via TBM reports). The controls are summarised as
follows:
·
A
minimum 8-week automatic delay to all permanent, temporary,
interim, agency or casual recruitments unless over-ridden by
exception by the relevant DMT due to service delivery
considerations, for example, to maintain staffing in services
requiring statutory minimum staffing levels such as residential
homes;
·
DMT
approval for any contract extensions;
·
DMTs
to consider the health and well-being impact of delayed
recruitments on existing staff, particularly in teams or services
where multiple or longstanding vacancies already exist and further
delays may place undue pressure on existing members of
staff;
·
2023/24 Approved
Savings: development of alternative recovery or mitigation measures
to address any forecast underachievement of approved
savings;
·
Identifying
underspending opportunities: DMTs will review underspending or
break-even services to explore whether greater underspending or
moving into underspend can be achieved to assist the
position;
·
DMT-specific
financial management actions including:
o Imposing
financial transaction limits above which senior management (head of
service, Assistant Director or Director) approval will be
required;
o Similarly,
reviewing any local schemes of delegation to managers for spending
decisions, for example, authorisation of adult or children’s
social care packages, and considering whether or not to review the
delegations;
o Imposing a
moratorium or limit on certain types of non-critical expenditure
where possible;
o Similarly,
setting target reductions for certain types or categories of
expenditure where this can be done without destabilising service
delivery;
o Curtailing or
‘value-engineering’ one-off or project spend or
exploring alternative funding solutions;
o Exploring
alternative funding to relieve pressure on the revenue budget e.g.
bids for grants, income generation, invest-to-save business cases,
etc.
·
Capital Schemes:
Consideration should also be given to ‘pausing’ or
curtailing capital schemes, particularly those that are supported
by borrowing, however, any delay of capital spend increases cash
balances which attracts investment income and is therefore
financially beneficial. If borrowing is involved, an even greater
saving may be possible although this will often not be realised
until the following financial year. The council’s Capital
Programme will be reviewed as part of the budget setting process
for next year but some schemes could immediately be paused. This
may require committee approvals which will be advised by the Chief
Finance Officer and Monitoring Officer as appropriate.
These escalated controls with ELT
oversight will remain in place until the forecast position improves
at which time it may be possible to relax measures in whole or in
part.
13
FINANCIAL AND OTHER IMPLICATIONS
Financial Implications:
13.1
The financial implications are covered in the main body of the
report. Financial performance is kept under review on a monthly
basis by the Executive Leadership Team and the management and
treatment of forecast risks is considered by the Audit &
Standards Committee as part of its review of strategic risks.
Finance Officer Consulted: Jeff
Coates
Date: 20th June 2023
Legal Implications:
13.2
Decisions taken in relation to the capital and revenue budget must
enable the council to observe its legal duty to achieve best value
by securing continuous improvement in the way in which its
functions are exercised, having regard to a combination of economy,
efficiency and effectiveness. The council must also comply with its
general fiduciary duties to its Council Tax payers by acting with
financial prudence, and bear in mind the reserve powers of the
Secretary of State under the Local Government Act 1999 to limit
Council Tax & precepts.
Lawyer Consulted: Elizabeth
Culbert
Date: 23rd June 2023
Equalities Implications:
13.3
There are no direct equalities implications arising from this
report.
Sustainability Implications:
13.4
Although there are no direct sustainability implications arising
from this report, the council’s financial position is an
important aspect of its ability to meet council priorities
including Carbon Neutral priorities set out in the Corporate
Plan.
Risk and Opportunity Management Implications:
13.5
The council’s revenue budget and Medium Term Financial
Strategy contain risk provisions to accommodate emergency spending,
even out cash flow movements and/or meet exceptional items. The
council maintains a recommended minimum working balance of
£9.000m to mitigate these risks. The council also maintains
other general and earmarked reserves and contingencies to cover
specific project or contractual risks and commitments.
SUPPORTING DOCUMENTATION
Appendices:
1.
Financial Dashboard Summary
2.
Revenue Budget RAG Rating
3.
Revenue Budget Performance
4.
Summary of 2023/24 Savings Progress
5.
Capital Programme Performance
6.
New Capital Schemes